Views: 0 Author: Site Editor Publish Time: 2013-12-20 Origin: Site
Many times, the new people buy back generator sets that do not operate according to the requirements of the sales staff or instructions. In the initial operation, the load is small, so black smoke failure occurs.
Haixing learned that a hospital user was working on the machine when starting the machine. He had to run the machine with a load when starting the machine. However, the customer did not notice that the load must be brought to the generator set more than 50%. They only brought a 20KW lighting system, and the load only accounted for 6.7% of the total load of the generator set, which did not meet the specified requirements, so black smoke was emitted.
In the initial stage of use, the new diesel engine should be loaded at 50%-80% and after 60 hours of running-in, then the new machine should be run-in period. Diesel engines should not be in long-term idle operation and low-load operation during the run-in period and normal working period after the run-in period.
So after you buy the new equipment, you will have an operation and learning process, which can be learned from the sales staff, or you can view the technical manual in detail to avoid unexpected problems.