18553382068 13951158508
News Center
front page / News Center / Technical support / Generator unit performance requirements 24 standards

Generator unit performance requirements 24 standards

Views: 0     Author: Site Editor     Publish Time: 2011-03-24      Origin: Site

Inquire

wechat sharing button
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
sharethis sharing button

Jiangsu Haixing Power Technology Co., Ltd. has been engaged in the generator set industry for many years and has detailed standards for the performance indicators of diesel generator sets . The performance of generator sets is something that enterprises are more concerned about. Only generator sets with excellent performance can provide customers with a complete power supply system.
1. Appearance requirements
(1) The boundary size, installation size and connection size of the diesel generator set are all subject to factory drawings approved by the prescribed procedures. Our Jiangsu Haixing Dynamics believes that this is very important. If you don't think about it first, the subsequent installation will become a big problem.
(2) The welding of the unit should be firm, the welds should be uniform, and there should be no defects such as welding penetration, undercuts, slag inclusions and pores. The welding slag and welding medicine should be cleaned; the paint film should be uniform, without obvious cracks or falling off; the plating layer should be smooth, without leakage plating spots, rust, etc.; the unit fasteners should not be loose.
(3) The electrical installation should comply with the circuit diagram, and there should be obvious signs that it is not easy to fall off at the connections of each conductor of the unit.
(4) There should be terminals with good grounding.
(5) Complete content of the sign
2. Insulation resistance and insulation strength requirements
(1) Insulation resistance: The insulation resistance of each independent electrical circuit to the ground and between the circuit should be greater than 2M
(2) Insulation strength: The independent electrical circuits of the unit should be able to withstand the AC test voltage for 1 minute, and there should be no breakdown or flickering.
Circuit voltage <100V 750V Test voltage ≥100V 1440V
3. Phase sequence requirements. Haixing Power believes that the phase sequence of the terminals of the diesel generator set control screen should be sorted from left to right or from top to bottom from front of the control screen.
4. Maintain the requirements for preparing for operation status. The unit should have a heating device to ensure that the oil temperature and cooling medium temperature during emergency start-up and rapid loading are not less than 15℃.
5. Reliability check for automatic power supply and automatic shutdown
(1) After connecting to the start command of automatic control or remote control, the diesel power generation should be able to start automatically.
(2) Haixing Power believes that when the unit fails automatically after the unit starts automatically, a startup failure signal should be sent; when a backup unit is provided, the program startup system should be able to automatically pass the startup command to another backup unit.
(3) The time from issuing the automatic start command to supply power to the load should not exceed 3 minutes
(4) After the diesel generator is successfully started automatically, the first load should not be less than 50% of the calibration load.
(5) After connecting to the shutdown command of automatic control or remote control, the unit should be able to shut down automatically; for backup units used in conjunction with the mains power grid, when the power grid returns to normal, the diesel generator should be able to switch automatically or shut down automatically, and the shutdown delay time of the shutdown method should comply with the product technical conditions.
6. Voltage steady-state adjustment rate ≤250KW >250KW 3% 2%
7. Voltage transient adjustment rate ≤250KW >250KW 20% 15%
8. Voltage stability time ≤250KW >250KW ≤2s ≤1.5s
9. Voltage volatility ≤250kw >250kw 0.8% 0.5%
10. Frequency steady-state adjustment rate ≤250kw >250kw 3% 3%
11. Frequency transient adjustment rate ≤250kw >250kw 9% 9%
12. Frequency stability time ≤250kw >250kw 5s ≤5s
13. Frequency volatility ≤250kw >250kw ≤0.8% ≤0.5%
14. Automatic start success rate. The automatic startup success rate is no less than 99%.
15. No-load voltage setting range requirements. Haixing Power believes that the no-load voltage setting range of the unit is not less than 95%-105% calibration voltage.
16. Automatic supply function requirements. The unit should be able to automatically charge the starter battery.
17. Automatic protection function requirements. Haixing Power believes that the unit should have phase-deficiency, short circuit (not greater than 250KW), overcurrent (not greater than 250KW), overspeed, high water temperature and low oil pressure protection.
18. Sine distortion rate of line voltage waveform. Haixing Dynamics believes that under no-load calibration voltage and calibration frequency, the sinusoidal distortion rate of the linear voltage waveform is <5%.
19. Voltage deviation under three-phase asymmetric load. Haixing Power believes that under a three-symmetric load of 25% and a resistive load of 25% calibration phase power is added to any phase, the unit should be able to work normally, with the maximum or minimum value of the line voltage and 5% of the average value of the three-line voltage.
20. Noise. Haixing Power believes that the average noise sound pressure value 1m away from the unit diesel engine and generator: ≤250KW >250KW ≤102db(A) ≤108db(A)
21. Fuel consumption rate. The unit calibration power is 120 22. Diesel generator consumption rate. The unit calibration power is >40KW, and the unit consumption rate is ≤3.0G/KW.H
23. Operate test under calibration conditions. Haixing Power believes that under the specified working conditions, the unit can operate normally and continuously for 12 hours in calibration conditions (including 10% overload operation for 1 hour), and the diesel generator set should be free of water and air leakage.
24. Remote control, remote signal and telemetry performance
(1) Intelligent unit generator
sets with a power supply of more than 200KW should be intelligent, and their monitoring content and interface requirements are as follows:
① Remote control: on/off, emergency stop, switch the main and spare units.
② Remote signal: working state (operation/stop), working mode (automatic/manual), main units, overvoltage, undervoltage, overcurrent, frequency
③ Telemetry: three-phase output voltage, three-phase output dynamic battery voltage, output power.
④Interface: It should have a communication interface (RS-232 and RS-485/422) and be able to provide a complete communication protocol.
(2) Non-intelligent unit
Haixing Power believes that non-intelligent units with 200KW or below have no remote control, remote signal and telemetry requirements.

More than 20 years of experience in gas power generation engineering application. It has the ability to provide integrated operation services of technology, equipment, engineering design, construction, operation and services.

Contact us

18553382068
13951158508
2260661851@qq.com
2260661851
www.hxdlkj.com
all rights reserved Su ICP No. 19030651-1 Sitemap